slava.energy: UK renewable energy projects
Three Maids Hill Solar Farm
REPD record 8011. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 25 MW
- Status
- Operational
- Operator
- Environmenta Asset Management
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Winchester
- Planning reference
- 20/02311/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-01-23
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-21: Planning Application Submitted
- 2021-05-19: Planning Permission Granted
- 2023-01-01: Operational
- 2024-05-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8011. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.