slava.energy: UK renewable energy projects
National Grid Axminster Substation
REPD record 8036. Status: Planning Application Submitted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Application Submitted
- Operator
- Harbour Energy
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- East Devon
- Planning reference
- 20/1877/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-09-07: Planning Application Submitted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8036. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.