slava.energy: UK renewable energy projects
Brindley Close (Extension)
REPD record 8045. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 6 MW
- Status
- Under Construction
- Operator
- Public Power Solutions
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Swindon
- Planning reference
- S/20/0850
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-01-25
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-07-13: Planning Application Submitted
- 2020-09-04: Planning Permission Granted
- 2022-05-01: Under Construction
- 2023-09-04: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8045. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.