Larks Green Solar Farm
REPD record 8051. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 70 MW
- Status
- Operational
- Operator
- Enso Energy & Iron Acton Green
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- South Gloucestershire
- Planning reference
- P20/13909/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-05-16
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-08-21: Planning Application Submitted
- 2021-01-05: Planning Permission Granted
- 2021-12-01: Under Construction
- 2023-05-02: Operational
- 2024-01-05: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8051. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.