slava.energy: UK renewable energy projects
Blenheim Net Zero Estate
REPD record 8069. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 5 MW
- Status
- Under Construction
- Operator
- Vanburgh Unit Trust
- County
- Oxfordshire
- Region
- South East
- Country
- England
- Planning authority
- West Oxfordshire
- Planning reference
- 20/01817/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-08-12: Planning Application Submitted
- 2021-01-08: Planning Permission Granted
- 2024-01-01: Under Construction
- 2024-01-08: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8069. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.