Mill Lane, Nursling - Battery Storage Facility
REPD record 8099. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 20 MW
- Status
- Under Construction
- Operator
- Gerard Hall Energy
- County
- Hampshire
- Region
- South East
- Country
- England
- Planning authority
- Test Valley
- Planning reference
- 19/02772/FULLS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-03-02
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-11-26: Planning Application Submitted
- 2020-05-13: Planning Permission Granted
- 2023-01-01: Under Construction
- 2023-05-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8099. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.