slava.energy: UK renewable energy projects
Litchardon Cross Solar Farm
REPD record 8101. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Aura Power & Infinis Energy Services
- County
- Devon
- Region
- South West
- Country
- England
- Planning authority
- North Devon
- Planning reference
- 71708
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2024-02-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-07-24: Planning Application Submitted
- 2021-05-14: Planning Permission Granted
- 2022-09-01: Under Construction
- 2024-05-14: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8101. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.