Cotmoor Solar Farm
REPD record 8118. Status: Appeal Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Appeal Granted
- Operator
- JBM Solar Projects
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Newark and Sherwood
- Planning reference
- 20/01242/FULM
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-07-10: Planning Application Submitted
- 2021-03-04: Planning Permission Refused
- 2021-07-23: Appeal Lodged
- 2022-02-18: Appeal Granted
- 2022-02-18: Planning Permission Granted
- 2025-02-18: Planning Permission Expired