Kemble Wick
REPD record 8136. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Aura Power
- County
- Gloucestershire
- Region
- South West
- Country
- England
- Planning authority
- Cotswold
- Planning reference
- PL/2021/06919
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-04-14
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-07-27: Planning Application Submitted
- 2022-03-25: Planning Permission Granted
- 2025-02-01: Under Construction
- 2026-02-01: Operational
- 2027-03-25: Planning Permission Expired
Open this area on the map