Gleneagles Hotel Biomass Boiler Plant Room
REPD record 8188. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 1.2 MW
- Status
- Operational
- Operator
- AMP Energy Services Limited
- County
- Tayside
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Perth and Kinross
- Planning reference
- 20/01615/FLL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-06-28
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-11-19: Planning Application Submitted
- 2021-02-04: Planning Permission Granted
- 2021-10-01: Operational
- 2024-01-19: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8188. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.