slava.energy: UK renewable energy projects
Cupar Wastewater Treatment Works Solar Farm
REPD record 8205. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.62 MW
- Status
- Operational
- Operator
- Scottish Water (Dundee)
- County
- Fife
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Fife
- Planning reference
- 20/02141/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-11-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-23: Planning Application Submitted
- 2021-01-19: Planning Permission Granted
- 2021-07-19: Operational
- 2023-12-17: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8205. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.