slava.energy: UK renewable energy projects
Arlington Energy Battery Storage
REPD record 8207. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Under Construction
- Operator
- Arlington Energy Limited
- County
- East Sussex
- Region
- South East
- Country
- England
- Planning authority
- Rother
- Planning reference
- RR/2020/1817/P
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-01-12
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-07: Planning Application Submitted
- 2021-02-09: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8207. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.