slava.energy: UK renewable energy projects
Kirby Road Solar Panels
REPD record 8212. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.49 MW
- Status
- Under Construction
- Operator
- Syzygy Consulting
- County
- Leicestershire
- Region
- East Midlands
- Country
- England
- Planning authority
- Blaby
- Planning reference
- 20/1111/PT14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-01-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-11-05: Planning Application Submitted
- 2021-02-16: Planning Permission Granted
- 2023-12-15: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8212. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.