Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 28 MW
- Status
- Operational
- Operator
- Eku Energy
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Thurrock
- Planning reference
- 20/01491/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-30: Planning Application Submitted
- 2021-02-19: Planning Permission Granted
- 2024-02-05: Planning Permission Expired
- 2025-08-11: Operational