British Geological, Keywork Solar Panels
REPD record 8222. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 0.62 MW
- Status
- Under Construction
- Operator
- British Geological Survey Head Office
- County
- Nottinghamshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Rushcliffe
- Planning reference
- 20/02647/PA14J
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-05-17
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-10-28: Planning Application Submitted
- 2021-01-13: Planning Permission Granted
- 2023-12-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8222. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.