Brentwood nergy Storage System
REPD record 8249. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- Anesco Limited
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Brentwood
- Planning reference
- 20/01800/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-07-08
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-12-07: Planning Application Submitted
- 2021-05-21: Planning Permission Granted
- 2024-05-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8249. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.