slava.energy: UK renewable energy projects

Minchens Lane Battery Storage Facility

REPD record 8434. Status: Operational.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
100 MW
Status
Operational
Operator
Penso Power (BW ESS)
County
Hampshire
Region
South East
Country
England
Planning authority
Basingstoke and Deane
Planning reference
21/00349/FUL
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2026-03-09

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8434. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.