Burneside Mill, Burneside
REPD record 8440. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1 MW
- Status
- Operational
- Operator
- Burenside Community Energy Limited
- County
- Cumbria
- Region
- North West
- Country
- England
- Planning authority
- Westmorland and Furness
- Planning reference
- SL/2021/0107
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-01-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-02-03: Planning Application Submitted
- 2021-04-30: Planning Permission Granted
- 2021-05-24: Under Construction
- 2021-06-15: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8440. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.