slava.energy: UK renewable energy projects
Crossens Pumping Station - Solar Array
REPD record 8513. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 1 MW
- Status
- Planning Permission Granted
- Operator
- Environment Agency
- County
- Merseyside
- Region
- North West
- Country
- England
- Planning authority
- Sefton
- Planning reference
- 2021/0937/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-02-22
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-08-19: Planning Application Submitted
- 2022-02-25: Planning Permission Granted
- 2025-02-25: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8513. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.