slava.energy: UK renewable energy projects
Langleys Lane - Electricity Generation Plant
REPD record 8840. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Landfill Gas
- Capacity
- 6 MW
- Status
- Operational
- Operator
- Biogas Technologies Limited
- County
- Somerset
- Region
- South West
- Country
- England
- Planning authority
- Somerset
- Planning reference
- 2021/0419/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-11-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-01-01: Under Construction
- 2021-03-12: Planning Application Submitted
- 2021-07-01: Operational
- 2021-08-13: Planning Permission Granted
- 2024-08-13: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8840. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.