slava.energy: UK renewable energy projects
Meadow Lane Solar Farm
REPD record 8897. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 19.6 MW
- Status
- Under Construction
- Operator
- Gresham House & Anesco Limited
- County
- Derbyshire
- Region
- East Midlands
- Country
- England
- Planning authority
- Amber Valley
- Planning reference
- AVA/2021/0313
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-04-09: Planning Application Submitted
- 2021-10-21: Planning Permission Granted
- 2023-03-28: Under Construction
- 2024-10-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8897. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.