slava.energy: UK renewable energy projects
Drumshoreland Road Battery Storage Facility
REPD record 8920. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 49.9 MW
- Status
- Operational
- Operator
- Engie Regeneration Limited
- County
- West Lothian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- West Lothian
- Planning reference
- 0255/FUL/22
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-08-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-04-01: Planning Application Submitted
- 2022-07-07: Planning Permission Granted
- 2025-07-07: Planning Permission Expired
- 2026-07-28: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8920. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.