slava.energy: UK renewable energy projects
Docks Way Solar Farm
REPD record 8923. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 2.37 MW
- Status
- Planning Permission Granted
- Operator
- Newport City Council
- County
- Gwent
- Region
- Wales
- Country
- Wales
- Planning authority
- Newport
- Planning reference
- 21/0346
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2021-12-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-03-25: Planning Application Submitted
- 2021-12-01: Planning Permission Granted
- 2026-12-01: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 8923. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.