Little Staughton Solar Farm
REPD record 8991. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 50 MW
- Status
- Planning Permission Granted
- Operator
- Nextpower Spv 12 Limited
- County
- Cambridgeshire
- Region
- Eastern
- Country
- England
- Planning authority
- Huntingdonshire
- Planning reference
- 22/01813/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-02-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-09-13: Planning Application Submitted
- 2024-12-04: Planning Permission Granted
- 2027-12-04: Planning Permission Expired