slava.energy: UK renewable energy projects
Gonerby Moor, Great Gonerby - Solar Farm
REPD record 9096. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 60 MW
- Status
- Operational
- Operator
- Sonnedix
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- South Kesteven
- Planning reference
- S21/1018
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-07-13
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-05-21: Planning Application Submitted
- 2021-11-03: Planning Permission Granted
- 2024-11-03: Planning Permission Expired
- 2025-05-01: Under Construction
- 2026-06-26: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9096. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.