Alfreton WtE

REPD record 913. Status: Planning Application Withdrawn.

Facts

As published by REPD, release Q3 2026.

Technology
Advanced Conversion Technologies
Capacity
5.2 MW
Status
Planning Application Withdrawn
Operator
Warwick Energy
County
Derbyshire
Region
East Midlands
Country
England
Planning authority
Amber Valley
Planning reference
CW6/0210/203
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2014-01-21

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 913. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.