slava.energy: UK renewable energy projects
Canford
REPD record 916. Status: Decommissioned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 1 MW
- Status
- Decommissioned
- Operator
- New Earth Energy
- County
- Dorset
- Region
- South West
- Country
- England
- Planning authority
- Bournemouth, Christchurch and Poole
- Planning reference
- APP/09/00810/C and APP/11/01669/C
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-11-20
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-07-20: Planning Application Submitted
- 2009-09-11: Planning Permission Granted
- 2011-07-01: Operational
- 2011-09-11: Planning Permission Expired
Open this area on the map