slava.energy: UK renewable energy projects
Forth Ports Ltd 2 (Grangemouth)
REPD record 92. Status: Planning Permission Expired.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 85 MW
- Status
- Planning Permission Expired
- Operator
- Grangemouth Renewable Energy
- County
- Falkirk
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- EC00005229
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-11-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-09-17: Planning Application Submitted
- 2013-06-03: Planning Permission Granted
- 2018-06-03: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 92. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.