Lincoln EFW
REPD record 924. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 16.4 MW
- Status
- Operational
- Operator
- Lincolnshire County Council
- County
- Lincolnshire
- Region
- East Midlands
- Country
- England
- Planning authority
- North Kesteven
- Planning reference
- N43\1186\08
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-05-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2008-11-28: Planning Application Submitted
- 2009-03-16: Planning Permission Granted
- 2011-05-30: Under Construction
- 2014-03-14: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 924. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.