Bedminster BioEnergy Facility
REPD record 933. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 8 MW
- Status
- Abandoned
- Operator
- Bedminster BioEnergy Solution
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire West and Chester
- Planning reference
- not held by REPD
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2012-02-27
Status history
Dated status events as published by REPD, release Q3 2026.
- 2007-12-14: Planning Application Submitted
- 2008-04-21: Planning Permission Granted