South Farm Solar Park
REPD record 9361. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Voltalia UK
- County
- Dorset
- Region
- South West
- Country
- England
- Planning authority
- Dorset
- Planning reference
- 2/2019/0850/PAEIA
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-12-21
Status history
Dated status events as published by REPD, release Q3 2026.
- 2011-03-05: Planning Permission Expired
- 2019-06-21: Planning Application Submitted
- 2020-03-05: Planning Permission Granted
- 2021-01-07: Under Construction
- 2022-12-16: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9361. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.