Capenhurst Lane, Capenhurst - Battery storage
REPD record 9377. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 57 MW
- Status
- Under Construction
- Operator
- HD888CAP Limited
- County
- Cheshire
- Region
- North West
- Country
- England
- Planning authority
- Cheshire West and Chester
- Planning reference
- 21/02404/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-09-15
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-06-03: Planning Application Submitted
- 2022-03-11: Planning Permission Granted
- 2022-09-01: Under Construction
- 2024-10-21: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9377. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.