Barleylands Solar Farm
REPD record 9392. Status: Revised.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- not held by REPD
- Status
- Revised
- Operator
- Enso Energy Limited
- County
- Essex
- Region
- Eastern
- Country
- England
- Planning authority
- Basildon
- Planning reference
- 22/00411/FULL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-04-19
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-04-05: Planning Application Submitted
- 2023-03-23: Planning Permission Granted
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9392. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.