slava.energy: UK renewable energy projects
Belfast Harbour Estate
REPD record 957. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 14.9 MW
- Status
- Under Construction
- Operator
- Bombardier
- County
- Co. Down
- Region
- Northern Ireland
- Country
- Northern Ireland
- Planning authority
- Belfast
- Planning reference
- Z/2012/1387/F
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-06-04
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-12-19: Planning Application Submitted
- 2014-01-23: Planning Permission Granted
- 2016-01-25: Under Construction
- 2019-01-23: Planning Permission Expired
Position not held by REPD.
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 957. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.