REPD record 9578. Status: Under Construction.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 3.99 MW
- Status
- Under Construction
- Operator
- Rochdale Metropolitan Borough Council
- County
- Greater Manchester
- Region
- North West
- Country
- England
- Planning authority
- Rochdale
- Planning reference
- 20/00687/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2023-10-11
Status history
Dated status events as published by REPD, release Q3 2026.
- 2020-06-03: Planning Application Submitted
- 2020-08-10: Planning Permission Granted
- 2023-04-01: Under Construction