Kilmarnock South Substation - Battery storage
REPD record 9696. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 300 MW
- Status
- Operational
- Operator
- Zenobe Energy
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Scottish Government (S36)
- Planning reference
- ECU00003435
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-10
Status history
Dated status events as published by REPD, release Q3 2026.
- 2022-02-22: Planning Application Submitted
- 2024-01-26: Under Construction
- 2026-01-21: Operational
- 2028-03-10: Planning Permission Expired