Pollington Energy Park
REPD record 97. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 53 MW
- Status
- Abandoned
- Operator
- Dalkia
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Leeds
- Planning reference
- S36
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2014-05-07
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-12-16: Planning Application Submitted
- 2011-12-22: Planning Permission Granted
- 2016-12-22: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 97. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.