Invergordon EfW

REPD record 971. Status: Appeal Refused.

Facts

As published by REPD, release Q3 2026.

Technology
EfW Incineration
Capacity
4 MW
Status
Appeal Refused
Operator
Combined Power And Heat (Highlands)
County
Highland
Region
Scotland
Country
Scotland
Planning authority
Highland
Planning reference
08/00455/FULRC
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2019-12-17

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map