Milton Keynes Waste Recovery Park
REPD record 975. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 7 MW
- Status
- Operational
- Operator
- AmeyCespa
- County
- Buckinghamshire
- Region
- South East
- Country
- England
- Planning authority
- Milton Keynes
- Planning reference
- 13/00861/FULEIS
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2019-08-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2013-04-26: Planning Application Submitted
- 2013-07-12: Planning Permission Granted
- 2014-06-03: Under Construction
- 2016-07-12: Planning Permission Expired
- 2018-03-01: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 975. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.