Low Farm, Flockton - Solar Photovoltaic Farm
REPD record 9770. Status: Planning Permission Granted.
Facts
As published by REPD, release Q3 2026.
- Technology
- Solar Photovoltaics
- Capacity
- 49.9 MW
- Status
- Planning Permission Granted
- Operator
- Downing LLP
- County
- West Yorkshire
- Region
- Yorkshire and Humber
- Country
- England
- Planning authority
- Kirklees
- Planning reference
- 2021/62/93644/E
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2025-09-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2021-09-14: Planning Application Submitted
- 2022-08-24: Planning Permission Granted
- 2025-08-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9770. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.