slava.energy: UK renewable energy projects
Rookery South
REPD record 979. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- EfW Incineration
- Capacity
- 65 MW
- Status
- Operational
- Operator
- Veolia/Covanta
- County
- Bedfordshire
- Region
- Eastern
- Country
- England
- Planning authority
- The Planning Inspectorate - National Infrastructure
- Planning reference
- EN010011
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2022-01-24
Status history
Dated status events as published by REPD, release Q3 2026.
- 2010-08-05: Planning Application Submitted
- 2011-10-13: Planning Permission Granted
- 2015-10-13: Planning Permission Expired
- 2018-01-15: Under Construction
- 2022-01-21: Operational
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 979. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.