Heckington Fen Solar Park - Battery Storage

REPD record 9807. Status: Planning Permission Granted.

Facts

As published by REPD, release Q3 2026.

Technology
Battery
Capacity
not held by REPD
Status
Planning Permission Granted
Operator
Ecotricity Limited
County
Lincolnshire
Region
East Midlands
Country
England
Planning authority
The Planning Inspectorate - National Infrastructure
Planning reference
EN010123
Turbines
not held by REPD
Turbine size
not held by REPD
Record last updated in REPD
2025-02-10

Status history

Dated status events as published by REPD, release Q3 2026.

Open this area on the map

Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 9807. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.