slava.energy: UK renewable energy projects
Boyndie Airfield Biomass
REPD record 99. Status: Abandoned.
Facts
As published by REPD, release Q3 2026.
- Technology
- Biomass (dedicated)
- Capacity
- 4 MW
- Status
- Abandoned
- Operator
- Boyndie Biomass
- County
- Grampian
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Aberdeenshire
- Planning reference
- APP/2009/2327
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2013-02-06
Status history
Dated status events as published by REPD, release Q3 2026.
- 2009-07-16: Planning Application Submitted
- 2010-02-24: Planning Permission Granted
- 2016-02-24: Planning Permission Expired
Open this area on the map
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 99. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.