Stonehill Energy Storage / Upper Minety
REPD record 20399. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 50 MW
- Status
- Operational
- Operator
- Penso Power (BW ESS)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 17/05526/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2017-06-29: Planning Application Submitted
- 2017-09-21: Planning Permission Granted
- 2019-12-01: Under Construction
- 2020-12-01: Operational