slava.energy: UK renewable energy projects
Stonehill Energy Storage / Lower Minety
REPD record 7773. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Battery
- Capacity
- 50 MW
- Status
- Operational
- Operator
- Penso Power (BW ESS)
- County
- Wiltshire
- Region
- South West
- Country
- England
- Planning authority
- Wiltshire
- Planning reference
- 19/11460/FUL
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2026-03-09
Status history
Dated status events as published by REPD, release Q3 2026.
- 2019-11-29: Planning Application Submitted
- 2020-02-07: Planning Permission Granted
- 2021-12-15: Under Construction
- 2022-12-15: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 7773. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.