Glasgow Renewable Energy and Recycling Centre (Waste AD)
REPD record 286. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Anaerobic Digestion
- Capacity
- 5 MW
- Status
- Operational
- Operator
- Viridor
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Glasgow City
- Planning reference
- 12/01631/DC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2018-01-30
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-14: Planning Application Submitted
- 2013-01-29: Planning Permission Granted
- 2013-11-18: Under Construction
- 2014-01-29: Planning Permission Expired
- 2017-12-15: Operational