slava.energy: UK renewable energy projects
Glasgow Renewable Energy and Recycling Centre (ACT)
REPD record 928. Status: Operational.
Facts
As published by REPD, release Q3 2026.
- Technology
- Advanced Conversion Technologies
- Capacity
- 10 MW
- Status
- Operational
- Operator
- Viridor
- County
- Strathclyde
- Region
- Scotland
- Country
- Scotland
- Planning authority
- Glasgow City
- Planning reference
- 12/01631/DC
- Turbines
- not held by REPD
- Turbine size
- not held by REPD
- Record last updated in REPD
- 2020-04-29
Status history
Dated status events as published by REPD, release Q3 2026.
- 2012-08-14: Planning Application Submitted
- 2013-01-29: Planning Permission Granted
- 2013-11-18: Under Construction
- 2014-01-29: Planning Permission Expired
- 2019-08-01: Operational
Open this area on the map
Other REPD records on the same site
Source: DESNZ Renewable Energy Planning Database (REPD), release Q3 2026. Record 928. Licence: Open Government Licence v3.0. Positions on the map come from REPD's own grid references.